Our new home build in Solivita got underway in May as the builder laid the forms for the foundation
Progress increased as the plumbing was laid, concrete was poured and the walls began to rise. We had the chance to check out the site in mid-June.
The roof went up on our new home in July and we were able to don hard hats and take a walkthrough. Jim from Taylor Morrison also let us walk through a finished Letizia model to get some measurements.
Our pre-drywall walkthrough occurred in September and we got the chance to review all of the fixture placements and ensure everything was where it was supposed to be.
We paid another visit to the future homesite in October now that the drywall was completed to check on the progress and gather more information for our pending move.
Jim sent us some new photos in early November. We saw that the flooring was being installed as well as the kitchen and bathroom cabinets and countertops. The master shower had also been tiled.
After Thanksgiving, we received another set of photos as we got closer to our closing date.
With our closing date scheduled for mid-December, we had our final walkthrough with Matt.